A NON-LINEAR OPTIMISATION APPROACH TO IN-PIT HAUL ROAD DESIGN

Dimitar Kaykov1, Danail Terziyski2, Kremena Arsova-Borisova3, Milan Stajić4

1University of Mining and Geology “St. Ivan Rilski”, 1700 Sofia; E-mail: dimitar.kaykov@mgu.bg
2University of Mining and Geology “St. Ivan Rilski”, 1700 Sofia; E-mail: d.terziyski @mgu.bg
3University of Mining and Geology “St. Ivan Rilski”, 1700 Sofia; E-mail: kremena.arsova@mgu.bg
4University of Belgrade, Technical Faculty in Bor, 19210 Bor; E-mail: mstajic@tfbor.bg.ac.rs
Corresponding author: dimitar.kaykov@mgu.bg

ABSTRACT. Truck haul costs, as one of the predominant operational costs for mining and quarrying operations, are known to be heavily dependent on the design parameters of haul roads. Furthermore, in-pit haul road design parameters determine the pit limits and therefore, the potential feasibility of the mining operation. Thus, when in search of an optimal solution in terms of in-pit haul roads, one should primarily consider the location of the in-pit haul road, its design features and the deriving operational costs regarding extraction and haul costs. A suitable objective function in this case may be the undiscounted profit for the ultimate pit design. However, for each considered scenario, truck and excavator operational costs can be calculated using simulation techniques for better accuracy. Furthermore, finding an optimal solution requires the execution of a reliable and efficient algorithm, depending on the shape of the objective function. Hence, a non-linear optimisation approach was proposed in this paper for solving the in-pit haul road optimisation problem, based on a simulation of the materials allocation, which was used for calculating the objective function. Design parameters were assumed to be predetermined, while the only variable used for finding an optimal solution was the location of the in-pit haul road inside the pit contour. In addition, two 1-D algorithms were compared for finding the optimal solution (Search with accelerated step size and 1-D Simplex method). Furthermore, two regression models are proposed (Multiple Linear Regression – MLR and Non-Linear Regression – NLR), which could identify the more feasible region for the in-pit haul road location and reduce the number of iterations required for convergence.

Key words: in-pit haul road, open-pit mine, design parameters, non-linear optimisation, simulation

DOI: https://doi.org/10.58903/u17190831

A NON-LINEAR OPTIMISATION APPROACH TO IN-PIT HAUL ROAD DESIGN

References

Akay, A. E., Aruga, K., Bettinger, P. & Sessions, J. (2013). Using optimisation techniques in designing forest roads and road networks. Bartın Orman Fakültesi Dergisi, 15 (1), (pp. 49-62). Retrieved from https://dergipark.org.tr/ en/pub/barofd/issue/3390/46709

Aleksandrova E. & Trifonova M. Otsenka ustoychivostta na otkosi s otchitane na riska. Nauchni trudove na Sayuza na uchenite v Bulgaria – Plovdiv, Seria B. Estetstveni i humanitarni nauki, tom HV, Nauchna sesia “Tehnika i tehnologii, estestveni i humanitarni nauki” 25-26th October 2012, Dom na uchenite, (pp. 107-111), ISSN 1311 – 9192, (in Bulgarian),

Aleksandrova, E. (2008). Vazmozhnosti za tehnologichno upravlenie na ustoychivostta na otkosite. Nauchna konferentsia s mezhdunarodno uchastie “Naukata v usloviyata na globalizatsia”, tom ІІІ, chast ІІ, 1-2 oktomvri, 2008, (pp. 337 – 341), Izdatelstvo “Daga-JK”, Kardzhali, ISBN 978-954-9634-33-4, (in Bulgarian)

Atkinson, T. (1992). Design and layout of haul roads, in SME Mining Engineering Handbook (2nd ed.), Society for Mining, Metallurgy, and Exploration, Inc., Littleton, Colorado, USA., (pp. 1334-1342), ISBN 978-0873351003

Hustrulid, W., Kuchta, M. & Martin, R. (2013). Open pit mine planning and design. (3rd Edition), CRC, UK, ISBN 978-1466575127

Ivanova, V., Karacholov, P., Malinova, D., Pavlov, P. & Balev, V. (2016). Geotehnicheski izsledvania na glinite ot dolnia horizont na vatreshnoto nasipite na rudnik “Troyanovo-1”, klon na “Mini Maritsa Iztok” EAD vav vrazka s vtorichnoto mu izzemvane. VII International Geomechanics Conference, 1 yuli 2016, Varna, (pp. 34-44), ISSN 1314-6467 (in Bulgarian).

Kecojevic, V. & Komljenovic, D. (2010). Haul truck fuel consumption and CO2 emission under various engine load conditions. Mining engineering, 62(12), 44-48.

Koprev, I. (2015). Rudnichni patishta. Sofia, Avangard Prima, Sofia, ISBN 978-619-160-529-3 (in Bulgarian)

Koprev, I., Aleksandrova, E. (2022). Otkrit dobiv na polezni izkopaemi. Sofia, Izdatelska kashta “Sv. Ivan Rilski”, ISBN 978-954-353-459-3, (in Bulgarian)

Liu, D. & Pourrahimian Y. (2021). A framework for open-pit mine production scheduling under semi-mobile in-pit crushing and conveying systems with the high-angle conveyor, Mining, 1(1). 59-79. https://doi.org/ 10.3390/mining1010005

Mohutsiwa, M. & Musingwini, C. (2015). Parametric estimation of capital costs for establishing a coal mine: South Africa case study. Journal of the Southern African Institute of Mining and Metallurgy, 115(8), 789-797. http://dx.doi.org/10.17159/2411-9717/2015/V115N8A17

Morales-Varela, N., Nancel-Penard, P. & Parra, A. An integer linear programming model for optimising open pit ramp design, 38th APCOM proceedings, Session 11, May 2017, Denver, Colorado, USA, (pp. 9-16)

Nancel-Penard, P., Parra, A., Morales-Varela, M., Díaz, C. & Widzyk- Capehart, E. (2019). Value-optimal design of ramps in open pit mining, Archives of Mining Sciences, 64(2), 399-413. DOI: 10.24425/ams.2019.128691

Panayotova, M., Vlaseva, E., Aleksandrova, E. & Bratkova, S. (2013). Vazdeystvie na dobiva i prerabotvaneto na polezni izkopaemi varhu okolnata sreda. Sofia, Izdatelska kashta “Sv. Ivan Rilski”, ISBN 978-954-353-213-1, (in Bulgarian)

Paricheh, M. & Osanloo, M. Determination of the optimum in-pit crusher location in open-pit mining under production and operating cost uncertainties, Proceedings of the 6th International Conference on Computer Applications in the Minerals Industries, 3-4 October 2016, Istanbul, Turkey (pp. 1–7).

Pavlov, P., Banov, M. & Totev, L. (2015). Environmental consequences of copper mining. 8. Freibergeb Geotechnik-Kolloquium 2015. Technische Universitaet – Bergakademie Freiberg, 18 Juni 2015, Gerrnany, (pp.177-182), ISBN 978-3-86012-517-5

Poniewierski, J. (2017). Pseudoflow explained. A discussion of Deswik pseudoflow pit optimisation in comparison to Whittle LG pit optimisation. Deswik Mining Consultants Pty Ltd.https://www.deswik.com/wp-content/uploads/2017/05/Pseudoflow-Explained.pdf

Rao S. S. (2009). Engineering optimisation. Theory and practice. John Wiley & Sons, Inc. DOI:10.1002/9780470549124

Saleki, M., Kakaie, R. & Ataei, M. (2019). Mathematical relationship between ultimate pit limits generated by discounted and undiscounted block value maximisation in open pit mining. Journal of Sustainable Mining. https://doi.org/10.1016/j.jsm.2019.03.003

Stoyanchev, G. (2014). Podzemen vagledobiv. IK “Dvorets na kulturata”, Pazardzhik, ISBN: 978-954-8944-26-7 (in Bulgarian).

Stoyanov, S. (1993). Optimizatsia na tehnologichni protsesi. Izdatelstvo Tehnika, Sofia. ISBN 954-03-0256-0 (in Bulgarian).

Terziyski, D. & Kaykov, D. (2022). Haul road design optimisation approach following technological constrains in open pit mining. Sustainable Extraction and Processing of Raw Materials, 3(3), 78–88. https://doi.org/ 10.58903/c16182123

Thompson, R., Peroni, R., & Visser, A. (2018). Mining haul roads: theory and practice (1st ed.). CRC Press. https://doi.org/10.1201/9780429491474

Yarmuch, J. L., Brazil, M., Rubinstein, H., & Thomas, D. A. (2020). Optimum ramp design in open pit mines. Computers & Operations Research. 115, 104739 https://doi.org/10.1016/j.cor.2019.06.013

https://rpmglobal.com/product/haulsim/ (Last accessed on 28th April 2023)